Reconstruction of Baku city, Buzovna – Mardakan – Qala motorway
2010 - 2016
Technical specifications and work volumes of the road:
Total length of the road
12,70 km
Width of traffic lane
3,50 m
Number of traffic lanes
4 lanes
Road pavement
265 000 m2
Thickness of asphalt-concrete pavement
240 mm
Earthworks
942 200 m3
Capping layer
83 400 m3
Base course
54 900 m3
Asphalt-concrete mixture
94 500 tons
Various diameter drainage pipes
2 750 pm
Concrete kerb stone
16 300 pm
Construction works were started in December, 2010.
Opening ceremony of Buzovna-Mardakan-Gala Motorway Part I was held on May 26, 2013.
During construction of the motorway the infrastructure has been renewed, lighting system has been established, three junctions have been constructed along the motorway.
Construction works were completed in 2016.